The true cost of unplanned downtime: how to calculate lost hours, repair and the payback of predictive maintenance
The cost of one stoppage is more than the repair invoice. We walk through lost production hours, repair and a realistic estimate of what early warning saves in one worked example, and show which assumption moves the result most.
The item that shows up in the maintenance budget is usually parts and labor. But when a line stops, the real cost is the value of the product that could not be made while it was down. That is why two plants can have the same repair invoice while one stoppage is far more expensive. Splitting the calculation into three parts moves the conversation from "what does maintenance spend" to "what does downtime cost us".
1. Cost per failure
The formula is simple:
- cost per failure = downtime hours × loss per hour + repair
An example line: 8 hours of downtime on average, a production loss of 50,000 TRY per hour, and 150,000 TRY of repair per failure.
- Loss: 8 × 50,000 = 400,000 TRY
- Repair: 150,000 TRY
- Total per failure: 550,000 TRY
Repair is less than a quarter of the total (150,000 / 550,000 ≈ 27%). The rest is invisible loss.
2. Annual cost
Assume 6 unplanned stoppages a year:
- annual cost = 6 × 550,000 = 3,300,000 TRY
- annual downtime = 6 × 8 = 48 hours
These two numbers are the most useful pair for making a maintenance meeting concrete: how much money, how many hours.
3. How much does early warning save?
Not every failure can be prevented. Vibration, temperature or current data shows some failures days ahead; others come suddenly. The calculation needs two honest assumptions:
- avoidable share: the percentage of failures that early warning can catch (25% in the example)
- planned-intervention ratio: what a caught failure costs as a planned stop, as a percentage of the unplanned cost (30% in the example)
The formula:
- savings = number of stoppages × avoidable share × cost per failure × (1 − planned-intervention ratio)
In the example: 6 × 0.25 × 550,000 × 0.70 = 577,500 TRY per year. Annual downtime also falls from 48 hours to 36, a reduction of 12 hours (48 × 0.25).
4. Payback on the investment
If the system costs 1,200,000 TRY, payback is 1,200,000 / 577,500 × 12 ≈ 24.9 months, roughly two years. How much does changing the avoidable share move the result?
- 10% → annual savings 231,000 TRY
- 20% → 462,000 TRY
- 30% → 693,000 TRY
- 40% → 924,000 TRY
Savings are directly proportional to the avoidable share, so that is the assumption most worth debating. Classifying your past failure records by asking "did this failure show a warning sign beforehand" turns the number from a guess into a measurement.
Four common mistakes
- Counting the repair invoice as the downtime cost and leaving out the lost hours.
- Not stating whether the hourly loss is based on gross revenue or contribution margin. Raw material and energy that are not consumed during a stop reduce the loss; say which one you used.
- Assuming an avoidable share close to 100%. Realistic starting values are low and rise as data accumulates.
- Deciding on a single scenario. Looking at four values, like the sensitivity table above, ties the decision to a range rather than to one assumption.
Try it with your own numbers
The unplanned downtime cost tool runs in your browser; the values you enter are not sent to any server. The defaults in the example are only examples, so enter your own line's numbers. For a predictive maintenance pilot, get in touch.
Let's discuss this for your plant
More notes
All notes →- 3 min readMTBF, MTTR and availability: three numbers, three different questionsMTBF says how often a machine fails, MTTR how quickly it comes back, availability what share of the time the line can produce. We calculate all three from one example, show which decision each one supports, and list the four most common mistakes.
- 3 min readBearing life L10: what it says and what it does not, with load, speed and reliabilityFrom the catalogue dynamic load rating to the basic rating life, then to the reliability and operating-condition adjustment: we calculate a bearing's expected life step by step, show why a small increase in load shortens life so much, and list the questions L10 does not answer.
- 3 min readPareto of downtime causes: 80/20 is not a law, it is a starting pointWe rank one month of downtime records by cause and work out the cumulative share. The example deliberately does not follow 80/20: five of eight causes make up 86.7% of the total. We show how to choose the threshold, how record quality distorts the result, and what comes after Pareto.